Pages

Sunday, 22 May 2016


Saturday, May 21, 2016

Update of IT Modernisation Project as on 31-03-2016

The latest position of implementation is as follows:

·     Primary Data Centre has started functioning at Navi Mumbai since 3rd April, 2013.

·     Disaster Recovery Centre has been powered on at Mysore on 15-05-15.

·   28014 Departmental Post offices including mail offices and administrative offices have been networked at single Wide Area Network (WAN) and connected to Data Centre.

·     Core Banking Solution (CBS) has been rolled out in 20494 Post Offices.

·     ATMs have been installed in 759 locations.

·     Core Insurance solution (CIS-PLI) has been rolled out in 25406 Post Offices.

·   CSI Wave-1: Implementation of IDAM (Identity and Access Management) and SSO (Single Sign on) are under progress in Mysore Division.

·  Other Wave-1 security components are at Data Centre level and they are under implementation.

·    Anti-virus installed in 74,500 desktops 
     
     Enterprise Monitoring System under CSI Wave-1 is a Data Centre level component and it is under implementation.

·      CSI wave 2 Roll out: CSI has been rolled out In Mysore Division from 01.10.2015.

·     Two HOs and Sixty three SOs were migrated to CSI in addition to NSH Mysore.

·     The following Legacy applications were integrated with CSI. 
      
     eMO 
     eMO ePayment 
     Register net/ Parcel net 
     Speed net 
     IPS 
     IFS 
     RMFS 
     NPS 
     UAT for Wave 2 & 3 solutions is in progress (Cycle 1 & 2 completed).

·    CSI Integration UAT III completed from 22-06-2015 to 27-06-2015 at Hyderabad.

·    Closure of defects of UAT III completed from 09th to 11th July 2015 at Hyderabad. 

      Dispatch of RH Handheld devices started.

·    3546 devices have been dispatched to Branch Post Offices of Pilot circles.

No comments:

Post a Comment